[BORDER AREA DEVELOPMENT PROGRAMME (BADP)]

REPORT FOR THE QUARTER ENDING 3rd QUARTER OCT-DEC 2011

Sl.No

Name of the Schemes / Project

Location

Year of
commence - ment of the scheme

Approved
outlay (in Lakhs)

Physical
target with date for completion of the work

 Executing Department

Progress Report

District

Block / Village

  1.  

 

Construction of 4/R/S/B & Multipurpose Hall at Chungthang School

North

Chungthang

2010-11

95

 

HRDD

Work Under Progress
(40%completed) work being delayed due to earthquack.

  1.  

 

Ambulance shuttle service under Lachung PHSC

North

Lachung

2010-11

6

 

Health Dept

Received

  1.  

 

Dairy Development and strengthening of Chungthang Milk Plant

North

Chungthang

 

50

 

AH & VS Department

Work Under Progress
(80% Complete)

  1.  

 

 

Establishment of Tibetan Mastiffs (dog) conservation cum Breeding centre at Lachen, North Sikkim.

North

Lachen

2008-09

29

2 yrs

AH & VS Department

Work Under Progress
(60% Complete)
Civil works completed and breeding stock will be inducted shortly.

  1.  

 

 

Construction of cold community Yak Centre cum fodder at Yaksey, Lachung

North

Lachung

2008-09

81.18

2 yrs

AH & VS Department

Work Under Progress
(80% Complete)

  1.  

 

 River training work along Bangea Khola at Limo Lachung

North

Lachung

2009-10

95

2 yrs

Irrigation Department

 100% Completed

  1.  

 

River training work at Chumsey at an estimated cost of Rs.75.00 lakhs

North

Lachung

2009-10

75

2 yrs

Irrigation Department

100% Completed

  1.  

Construction of River training work at Latong Lhukang under Lachen, North Sikkim

North

Lachen

2010-11

53.53

 

Irrigation Department

Work Under Progress
20% Completed

  1.  

Construction of Protective wall at Yangthang (1) Opposite Lazum House (2) Opposite Dotam House under Lachen, North Sikkim

North

Lachen

2010

53.43

 

Irrigation Department

30% Completed

  1.  

 

River training work at Toga, under Lachen Dzumsa in North Sikkim

North

Lachen

2008-09

100

 

Irrigation Department

Work Under Progress
(70% Complete)

  1.  

 

 

River training work along river Lachen chu (Teesta) below talam village under Lachen, North Sikkim,

North

Lachen

2008-09

150

2 yrs

Irrigation Department

Work Under Progress
(80% Complete)

  1.  

 

Const. of box drain at Tilling village under Lachung Dzumsa

North

Lachung

 

30

 

RM&DD

Completed

  1.  

 

Construction of 14 mtrs RCC bridge at Shapochu under Lachen Dzumsa

North

Lachen

2009-10

29.25

 

RM&DD

Completed

  1.  

 

 

Construction of 65 mtrs span SFB at Thangu to Phaka over Teesta khola under Lachen Dzumsa

North

Lachen

2009-10

51

 

RM&DD

Completed

  1.  

 

Construction of 14 mtrs Span RCC Foot bridge over Thomrachen, Lachen

North

Lachen

2009-10

26.25

 

RM&DD

75% Completed

  1.  

 

Steel bridge at Tasha under Lachen

North

Lachen

2009-10

10

 

RM&DD

60% Completed

  1.  

 

 

Construction of water supply scheme at Lachen Handloom and Handicraft center

North

Lachen

2009-10

9

 

RM&DD

Completed

  1.  

 

Protective work at Thomchi Tsechu at Lachung

North

Lachung

 

18.76

 

RM&DD

  95% Completed

  1.  

Construction of Box Drain at Phaka Village

North

Lachung

2010-11

7.00

 

RM&DD

Completed

  1.  

Construction of Box Drain at Pharey Village

North

Lachung

2010-11

6.00

 

RM&DD

75% Completed

  1.  

Construction of RWSS at Maltin Busty

North

Lachung

2010-11

7.00

 

RM&DD

  Completed

  1.  

Construction of RCC Bridge over Singba Chu

North

Lachung

2010-11

7.00

 

RM&DD

Work Yet to Start
(Tender Process Completed)

  1.  

Construction of Box Drain from Gyamthang to Khemdum

North

Lachung

2010-11

29.50

 

RM&DD

95% Completed

  1.  

Construction of Boundary Fencing of Lachung Check Post

North

Lachung

2010-11

20.56

 

RM&DD

35% Completed

  1.  

Construction of Box Drain at Leema Their

North

Lachung

2010-11

19.70

 

RM&DD

90% Completed

  1.  

Construction of suspension foot bridge over yakdung under Lachung Dzumsa

North

Lachung

2010-11

20.07

 

RM&DD

50% Completed

  1.  

Construction of CC Footpath from Toga to Chupta under Lachen

North

Lachen

2010-11

22.70

 

RM&DD

50% Completed

  1.  

Construction of CC footpath around Bamzay village under Lachen in North Sikkim.

North

Lachen

2010-11

17.07

 

RM&DD

30% Completed

  1.  

Construction of CC footpath from Thapgay to Naram Village under Lachen Dzumsa

North

Lachen

2010-11

18.47

 

RM&DD

40% Completed

  1.  

Construction of CC footpath from Shopachu to Chorten under Lachen in North Sikkim

North

Lachen

2010-11

17.94

 

RM&DD

65% Completed

  1.  

 

 

 

Providing river training work to left bank of Sharguphuchu at intake of Lachung Stage-II and provide to protection to water conductor and control gate

North

Lachung

2009-10

58

2 yrs

Energy & Power Dept

Work Under Progress
(70% complete)

  1.  

 

Establishment of Transit Camp cum Rest house at Lachung, North Sikkim

North

Lachung

2009-10

58

2 yrs

Forest Department

Work Completed

  1.  

 

 

Upgradation / Protective works and drainage system on approach road to khendun village

North

Lachung

2009-10

25

 

Roads & Bridges Department

60% Completed

  1.  

 

 

 

 

 

Const. of inspection bunglow at Yakthang, Lachen (Thangu). Total estimated cost RS.138.00 lakhs. Rs.30.00 lakhs sanctioned in 2007-08 and balance of Rs.108.00 lakhs in 2008-09 and 2009-10

North

Lachen

2007-08

138

2 yrs

Roads & Bridges Department

Work Under Progress
(90% Complete)

  1.  

 

 

Construction of Car-Park and wash room facilities at Bamzay Thangu, North Sikkim

North

Lachen

 

50.69

 

Tourism Department

Work Under Progress
(95% Complete)

  1.  

 

 

 

Const. of hot spring at Tarum under Lachen. Out of estimated cost of Rs.103.00 lakhs the committee approved Rs.1500 lakhs in 2008-09

North

Lachen

2008-09

103

2 yrs

Tourism Department

Work Complete

  1.  

 

 

 

Trekking route from sebong to Gay and Yathang to Khongkapu under Lachen in North Sikkim

North

Lachen

2009-10

75

 

Tourism Department

Work Under Progress
60% Completed

  1.  

 

Construction of Toursit Information centre i/c parking at Chungthang

North

Chungthang

2009-10

51

 

Tourism Department

50% Completed

  1.  

 

Beautification of Leydo park at Chungthang

North

Chungthang

2009-10

12.09

 

Tourism Department

Work 25% Completed

  1.  

 

Const. of Barrack of security forces at Thangu North Sikkim

North

Lachen

2009-10

90

2 yrs

Police Dept.

35% completed

 

TOTAL